Thurcroft 66kV Outdoor Compound

Dates: July 2020 – September 2020


Location: Thurcroft


Switch Power Distribution were involved in the installation of the 66kV outdoor compound at Thurcroft including installation of the bus bars, VTs, circuit breakers, disconnectors and earth switches, and installation of containment and multicores.